Grade-wise Ratios











Grade-wise Ratios | Complete Mix Ratio Guide M5 to M70 | MixDesignCalc 2026


Grade-wise Mix Ratios

MixDesignCalc Complete Reference 2026 — All Concrete Grades M5 to M70. IS 456:2000 Nominal Mix Ratios & IS 10262:2019 Design Mix Ratios. Cement Bags per m³, Sand & Aggregate per Bag, Batch Quantities & Interactive Grade Ratio Lookup Tool.

Look Up a Grade Ratio

All Concrete Grade Ratios — Overview 2026

Concrete grades in India range from M5 (very lean fill concrete) to M100+ (ultra-high performance). Each grade is associated with a mix ratio that expresses the proportions of cement, fine aggregate (sand), and coarse aggregate (stone). Below M30, IS 456:2000 Table 9 provides simplified nominal mix ratios that can be used for minor or non-critical works. For M30 and above, and for any work where consistency and economy are important, IS 10262:2019 design mix ratios are computed from actual material properties and give more accurate, more economical proportions.

Nominal vs Design Mix Ratio — The Essential Distinction

  • Nominal mix ratios (IS 456 Table 9): Fixed ratios by volume — same ratio regardless of material quality. Conservative (over-cemented to compensate for variable site quality). Permitted for M5–M25 only. Easy to use on site but wasteful of cement
  • Design mix ratios (IS 10262:2019): Computed ratios by mass — specific to actual materials tested. Economical (uses only the cement needed for strength and durability). Mandatory for M30+. More complex to compute but MixDesignCalc does it instantly
  • The number looks different: M20 nominal ratio = 1:1.5:3 (by volume) ≠ M20 design ratio ≈ 1:1.9:3.5 (by mass). They look different because: (1) one is by volume, one by mass; (2) nominal is over-cemented; (3) design ratio depends on actual aggregate SG and zone. Both are valid for their respective applications
  • Do not mix them up: Using a nominal ratio in mass batching (or vice versa) produces incorrect concrete. Always specify which basis (volume or mass) is being used when communicating a mix ratio

Interactive Grade Ratio Lookup — Click Any Grade 2026

Click any grade below to see its full mix ratio details — nominal ratio (where applicable), typical design mix ratio, bags per m³, per-bag quantities, and IS 456:2000 requirements.

Site Batch Quantity Calculator – Any Grade 2026

Enter a grade and volume to get the exact batch quantities per bag and total quantities for your project, with moisture correction for FA.

🧱 Batch Quantity Calculator — Any Grade
Get per-bag and total batch quantities from a grade selection. Uses typical IS 10262:2019 design mix proportions.










Complete Grade-wise Mix Ratio Master Table – M5 to M70 2026

← Scroll horizontally to see all columns →

Grade fck (MPa) Nominal Ratio (by vol) Design Mix Ratio (by mass, typical) Cement (kg/m³) Sand (kg/m³) Agg (kg/m³) Water (kg/m³) W/C Bags per m³ IS 456 Exposure Design Mix Required?
M5 5 1:5:10 1:5.3:10.7 ~220 ~745 ~1495 ~176 0.80 4.4 PCC fill No
M7.5 7.5 1:4:8 1:4.3:8.6 ~260 ~730 ~1460 ~182 0.70 5.2 PCC fill No
M10 10 1:3:6 1:3.2:6.4 ~315 ~700 ~1400 ~189 0.60 6.3 PCC No
M15 15 1:2:4 1:2.4:3.8 ~330 ~695 ~1115 ~198 0.60 6.6 Mild (PCC) Optional
M20 20 1:1.5:3 1:2.2:3.5 ~330 ~730 ~1155 ~182 0.55 6.6 Mild (RCC) Recommended
M25 25 1:1:2 1:1.9:3.0 ~370 ~710 ~1115 ~185 0.50 7.4 Moderate Recommended
M30 30 No nominal 1:1.8:2.8 ~400 ~715 ~1120 ~180 0.45 8.0 Severe MANDATORY
M35 35 No nominal 1:1.6:2.5 ~435 ~695 ~1100 ~174 0.40 8.7 Very Severe MANDATORY
M40 40 No nominal 1:1.5:2.3 ~460 ~680 ~1080 ~166 0.36 9.2 Extreme MANDATORY
M45 45 No nominal 1:1.3:2.1 (w SCM) ~390+SCM ~645 ~1200 ~155 0.32 ~10.0 Extreme MANDATORY
M50 50 No nominal 1:1.0:2.1 (w SCM) ~386+SCM ~560 ~1200 ~154 0.29 ~10.6 Extreme MANDATORY
M55 55 No nominal 1:0.9:1.9 (HPC) ~400+SCM ~530 ~1175 ~145 0.27 ~11.5 Extreme+ MANDATORY+specialist
M60 60 No nominal 1:0.8:1.8 (HPC) ~415+SCM ~505 ~1150 ~140 0.25 ~12.0 Extreme+ MANDATORY+specialist
M70 70 No nominal 1:0.7:1.7 (UHPC) ~445+SCM ~470 ~1090 ~125 0.22 ~13.5 Specialist Specialist mix design

Important Notes on the Grade-wise Ratio Table

  • Nominal ratios are by volume; design mix ratios are by mass — do not use these on the same basis. Always specify which system you are using when communicating ratios on drawings, specifications, or site instructions
  • Design mix ratios vary with materials — the values in the table are computed for OPC 53, Zone II river sand (SG 2.65), crushed granite (SG 2.68), and Good control (S=4.0 MPa). Your actual design mix ratio will differ if your materials have different SGs, FM, or you use a different cement grade
  • M45 and above ratios include SCM — the cement content shown is OPC only; total binder (OPC + GGBS/SF) is typically 480–560 kg/m³. The ratio shown is Total Binder : FA : CA
  • Bags per m³ shown for 50kg bags of cement (OPC only) — for SCM blends, additional material is needed in the SCM component; bags per m³ of OPC only will be lower than the total binder bags

Frequently Asked Questions – Grade-wise Mix Ratios 2026

Q: What is the mix ratio for M30 concrete?
M30 has no IS 456 nominal mix ratio — nominal mix is only permitted up to M25 per IS 456:2000 Table 9. M30 requires a design mix per IS 10262:2019. A typical M30 design mix (OPC 53, Moderate-to-Severe exposure, Zone II sand, 20mm crushed aggregate, S=4.0 MPa) produces a ratio of approximately 1:1.8:2.8 by mass with w/c = 0.45. The actual ratio for your project will depend on your specific material SG values and FA zone — use the MixDesignCalc IS 10262 calculator to compute your project-specific ratio.

Q: How many bags of cement per m³ for each grade?
Approximate cement bags (50kg) per m³ for IS 10262:2019 design mix, OPC 53, Zone II sand, 20mm crushed, Moderate/Severe exposure: M15 = 6.6 bags; M20 = 6.6 bags; M25 = 7.4 bags; M30 = 8.0 bags; M35 = 8.7 bags; M40 = 9.2 bags; M50 = 10.6 bags (OPC only — add SCM). For IS 456 nominal mix: M15 = 6.5 bags; M20 = 7.7 bags; M25 = 9.5 bags (higher than design mix due to conservative nominal proportioning). Use 8 bags per m³ as a rough planning figure for M30 in urban India.

Q: Can the same mix ratio be used for different grades by just changing water content?
No — this is a common misconception. Increasing water content while keeping other ingredients constant raises the w/c ratio, which reduces strength (not increases it). To move from M25 to M30 with the same workability, you must increase cement content (reduce w/c to achieve higher strength) and adjust aggregate proportions accordingly. The entire mix ratio changes when you change the grade. You cannot convert between grades by changing only one ingredient — all five steps of IS 10262 must be recomputed.

Q: What is the mix ratio for M50 concrete with silica fume?
A typical M50 HPC design mix with OPC 53 + 10% SF + 20% GGBS, 20mm crushed, Zone II sand, PCE SP 30% WR: OPC 386 kg | SF 39 kg | GGBS 106 kg | Water 154 kg | FA 559 kg | CA 1201 kg. Mix ratio based on total binder: 1 : 1.05 : 2.26 (Binder : FA : CA) with w/c (w/total binder) = 0.29. The ratio is very different from M20 or M25 because: (1) the low w/c drastically reduces water and increases cement; (2) HPC uses lower FA% (32% vs 38–40% for M25); (3) total binder includes SCM which displaces aggregate. Use the MixDesignCalc M50 calculator for project-specific proportions.