Mix Proportioning Basics











Mix Proportioning Basics | MixDesignCalc 2026 — Ingredient Roles, w/c Law, Aggregate Optimization & Worked Example


Mix Proportioning Basics

MixDesignCalc 2026 — Understanding How Concrete Mix Proportions Are Determined: Ingredient Roles, Abrams’ w/c Law, Aggregate Optimisation, IS 10262:2019 Table 2 Water Contents, Paste vs Aggregate Balance & Complete M30 Worked Example

IS 10262:2019 Table 2Abrams’ Law
Aggregate GradingFA/CA Balance
Paste VolumeM30 Worked Example

📖 Contents

  1. The Four Ingredients & Their Roles
  2. Abrams’ Water-Cement Ratio Law
  3. Water Content — The Master Variable
  4. IS 10262:2019 Table 2 — Water Content Reference
  5. Paste vs Aggregate Volume Trade-off
  6. Aggregate Optimisation — MSA & Grading
  7. FA/CA Split — IS 10262:2019 Table 3
  8. Durability-Governed Proportioning
  9. How Admixtures Change the Proportions
  10. Full Worked Example — M30, 100mm Slump

1. The Four Ingredients and Their Roles

IS 456:2000
IS 8112 / IS 12269 (Cement)
IS 383:2016 (Aggregate)

Concrete is a composite material made from four primary ingredients. Understanding what each ingredient does — and what controls its quantity — is the foundation of mix proportioning. Every proportioning decision is a balance between these four roles.

🏭
Cement
10–18%
By volume of concrete. The binder — reacts with water to form C-S-H gel (calcium silicate hydrate) that glues aggregate particles together. The most expensive ingredient (~60–70% of concrete cost). Its quantity is derived from water content and w/c ratio: C = W / (w/c). Should be minimised within IS 456 limits.
💧
Water
15–21%
By volume of concrete. Serves two roles: (1) chemically reacts with cement for hydration; (2) provides workability (fluidity for placement). Water is the single most critical variable — it controls both workability and w/c ratio. Excess water beyond hydration need increases porosity and reduces strength. Goal: minimise water to minimise cement.
🟡
Fine Aggregate (Sand)
25–35%
By volume of concrete. Particles <4.75mm (IS 383). Fills voids between coarse aggregate particles, improves workability, and contributes to surface finish. Too little FA → harsh mix, difficult to pump; too much FA → high water demand (more surface area to wet). Zone II sand is the IS 10262 reference.
🪨
Coarse Aggregate (Stone)
40–55%
By volume of concrete. Particles >4.75mm (IS 383). Provides strength through aggregate interlock and load transfer, reduces paste volume (economy), and governs MSA selection. Larger CA requires less surface area wetting → lower water demand → lower cement. IS 456 Cl.5.3.1 limits MSA by element geometry and bar spacing.
The fundamental rule: Only two ingredients directly affect concrete strength — cement and water (through the w/c ratio). Aggregates are essentially inert filler at normal concrete grades (M10–M40). The job of mix proportioning is to select the minimum water that gives adequate workability, then calculate the cement needed to achieve the design w/c, then fill the remaining volume with optimally graded aggregate.

2. Abrams’ Water-Cement Ratio Law

In 1918, Duff Abrams published his experimental finding that, for fully-compacted concrete made with the same materials, the compressive strength is determined primarily by the water-cement ratio alone, regardless of the absolute quantities of water and cement.

Abrams’ Law: f’c = K₁ / K₂^(w/c)

Where:
f’c = compressive strength
K₁ = empirical constant (~97 MPa for OPC, varying by cement type)
K₂ = empirical constant (~4.0 for OPC at 28 days)
w/c = water-cement ratio by mass

Simplified practical form (IS 10262 correlation for OPC 53):
fcm ≈ 58 × (0.51)^(w/c / 0.10) [approximate — verify by trial]

Or inversely: w/c ≈ (1.78 − fcm × 0.0145) [IS 10262 regression approximation]

The w/c Scale — Strength and Durability Together

The water-cement ratio is the single most important parameter because it governs both strength and durability simultaneously:

  • Strength (Abrams’ Law): Lower w/c → higher strength. Approximately every 0.05 reduction in w/c increases 28-day cube strength by 5–8 MPa for OPC 53.
  • Durability (permeability): Lower w/c → denser paste → lower permeability → better resistance to chloride, carbonation, sulfate attack. This is why IS 456 Table 5 limits maximum w/c by exposure class, independently of strength.

0.25UHPC
v.high str.
0.30M60+
HSC
0.35–0.40M40–M50
Extreme
0.45M30
Severe
0.50M25
Moderate
0.55–0.60M20
Mild
>0.65Lean
blinding

IS 456:2000 Table 5 — The Durability Override

Abrams’ Law gives the strength-based w/c. But IS 456 Table 5 may impose a lower (more restrictive) maximum w/c based on the exposure class. Design always uses the lower of the two:

Mild exposure: max w/c 0.60 — strength usually governs below M30
Moderate: max w/c 0.50 — durability governs from M20 upward
Severe: max w/c 0.45 — durability governs for M25–M30
Very Severe: max w/c 0.40 — durability always governs
Extreme: max w/c 0.35 — durability dominates completely

Why Abrams’ Law Works — The Micro-Scale Explanation

Cement hydration only needs about w/c = 0.23 to fully react (Powers, 1947). All water above this threshold forms capillary pores when it evaporates — and these pores weaken the paste. At w/c = 0.70, capillary porosity is ~40% of paste volume. At w/c = 0.35, it is ~15%. The direct relationship between capillary porosity and both strength and permeability explains why Abrams’ Law and IS 456 durability requirements both point to the same conclusion: lower is better, up to the minimum needed for workability.

3. Water Content — The Master Variable of Mix Proportioning

Water content (W, in L/m³) is the starting variable in the IS 10262:2019 calculation sequence — everything else follows from it. Once W is fixed and the design w/c is determined, cement content is simply C = W / w/c. Then aggregate fills the remaining volume. Reducing water content is the single most effective lever for simultaneously reducing cement content, improving strength, and improving durability.

What Controls Water Content?

The free water content required to achieve a given workability (slump) depends on three factors:

1. Maximum Aggregate Size (MSA)

Larger aggregate particles have less total surface area per unit volume than smaller particles. Less surface area = less water needed to wet the aggregate = lower water demand. Going from 10mm to 40mm MSA reduces water demand by approximately 30–35 L/m³ — saving roughly 65–75 kg/m³ of cement at the same w/c. This is the most powerful aggregate-side lever for cement economy.

2. Aggregate Shape and Texture

Crushed aggregate (angular, rough surface) has higher water demand than rounded natural gravel (smooth surface). IS 10262 Table 2 is calibrated for crushed aggregate — if using rounded gravel, reduce tabulated water by ~20 L/m³ (IS 10262 Note). Flaky or elongated aggregates dramatically increase water demand and should be minimised (IS 383: flakiness index ≤ 25%; elongation index ≤ 15%).

3. Target Slump (Workability)

Higher slump requires more water (or more SP). In IS 10262 Table 2, each 25mm increase in slump requires approximately 5–8 L/m³ more water. This water increase is proportional and also increases required cement (since w/c must be maintained). Using PCE SP to achieve slump without adding water is the engineered solution — SP provides workability without the water penalty.

Water Content Relationships:

Effect of MSA (crushed aggregate, 100mm slump):
10mm → ~222 L/m³ | 20mm → ~202 L/m³ | 40mm → ~176 L/m³
(Range: 10mm vs 40mm = 46 L/m³ difference → ~100 kg/m³ cement saving at w/c 0.45)

Effect of rounded aggregate: subtract ~20 L/m³ from crushed values
Effect of SP (PCE, 25% WR): multiply by (1 − 0.25) = 0.75
Effect of slump increase (25mm→100mm at 20mm MSA): +5 to +8 L/m³ per 25mm

Cement Content: C = W / (w/c)
Cost Impact: Each 10 L/m³ reduction in W → 22 kg/m³ less cement at w/c 0.45

4. IS 10262:2019 Table 2 — Free Water Content Reference

IS 10262:2019 Table 2 provides the reference water content in L/m³ for crushed angular aggregate at various MSA and slump combinations. This table is the starting point for the water content step — before any adjustment for aggregate type, admixture, or moisture condition. The values below are the IS 10262:2019 tabulated figures.

← Scroll

MSA (mm) Target Slump (mm)
25–50 51–75 76–100 101–125 126–150 151–175
10mm 208 215 222 228 234 240
12.5mm 200 207 213 219 225 231
16mm 196 200 206 212 218 223
20mm 190 196 202 208 213 217
25mm 184 188 193 199 204 208
40mm 168 172 176 181 185 189

Highlighted cell (green): 20mm MSA, 76–100mm slump = 202 L/m³ — the most common reference for M25–M35 structural concrete.

How to Apply the Table — Step by Step

  1. Select row: Based on the MSA you have chosen (limited by IS 456 Cl.5.3.1)
  2. Select column: Based on the target slump at placement (not at the plant — allow for transit loss of ~20–30mm for 30-minute transit)
  3. Read off water content from the table
  4. Adjust for aggregate type: If rounded gravel — subtract 20 L/m³. If recycled aggregate — add 15 L/m³
  5. Adjust for SP: Multiply by (1 − WR%), where WR% is the SP water reduction percentage. PCE SP at 1% dose typically gives 22–25% WR, so multiply by 0.75–0.78
  6. Result: This is the design free water content W to use in C = W / w/c

Common Confusion — Table 2 is for SSD Aggregates

IS 10262 Table 2 water contents assume aggregates in Saturated Surface-Dry (SSD) condition — pores full but surface dry. In practice, aggregates have surface moisture (wet) or are air-dry (below SSD). The batch water must be corrected:

If aggregate is wetter than SSD: reduce batch water by (surface moisture % × aggregate mass)
If aggregate is drier than SSD: increase batch water by (absorption deficit × aggregate mass)

IS 10262:2019 Clause 5.6 gives the correction formula. In monsoon season with wet river sand at 3% surface moisture, the water correction can be 50–60 L/m³ — entirely changing the mix if ignored.

5. Paste vs Aggregate Volume — The Fundamental Trade-off

In every cubic metre of concrete, the volumes of paste (cement + water + air + admixtures) and aggregate (FA + CA) must sum to exactly 1.0 m³. More paste means less aggregate, and vice versa. This trade-off is the core tension in mix proportioning.

Typical Volumetric Composition — M25 vs M60 (per m³)
M25 (w/c 0.50, 20mm, no SP)
Cement 12%
Water 17.5%
Air 2%
FA 27%
CA 41.5%
Paste = 31.5% | Aggregate = 68.5%
M60 HSC (w/c 0.28, SF 10%, PCE, 16mm)
OPC 15%
SF 5%
Water 13.5%
Air
FA 24%
CA 36%
SP
Paste = 35.5% | Aggregate = 60%

Consequences of Too Much Paste (High Cement)

  • Increased heat of hydration → thermal cracking in large sections
  • Higher drying shrinkage → more cracks
  • Reduced aggregate volume → lost aggregate interlock in HSC
  • Higher cost → 60–70% of concrete cost is cement
  • IS 456 Cl.8.2.5 cap at 550 kg/m³ total cementitious

Consequences of Too Little Paste (Low Cement)

  • Insufficient paste to coat and lubricate all aggregate surfaces → harsh, unworkable mix
  • Poor pump performance → blockages
  • Honeycombing → voids → strength and durability deficiency
  • Violation of IS 456 Table 5 minimum cement content

The Optimal Paste Volume Window

Research and practical experience show that for most structural concrete:

Paste volume 26–32% of total concrete volume is the practical sweet spot for most M20–M35 concrete with 20mm crushed aggregate. Below 26%: workability problems. Above 35%: excessive shrinkage and heat risk.

For HSC (M45–M60) with SF and PCE, paste volumes of 33–38% are typical — the dense SF-rich paste is less porous than standard paste, so higher paste volumes don’t carry the same shrinkage penalty.

The absolute volume calculation automatically determines paste volume: V_paste = V_cement + V_water + V_air + V_SP. Always check this value as a sanity check on your mix design.

6. Aggregate Optimisation — MSA and Grading

6.1 Selecting Maximum Aggregate Size (MSA)

MSA selection is governed by IS 456:2000 Clause 5.3.1, which sets three upper limits — the MSA must satisfy all three simultaneously:

MSA ≤ 1/4 × minimum cross-sectional dimension of the structural member
MSA ≤ 3/4 × clear spacing between bars (or between bar and formwork)
MSA ≤ (nominal cover − 5 mm)

Design MSA = min(all three constraints above)

Then choose the largest standard size ≤ design MSA:
Standard sizes: 10mm, 12.5mm, 16mm, 20mm, 25mm, 31.5mm, 40mm (IS 383:2016)

Practical MSA Selection Guide

  • Columns with dense reinforcement: 12.5–16mm (seismic columns: sometimes 10mm)
  • Beams, standard reinforcement: 20mm
  • Slabs, wide spacing: 20–25mm
  • Foundations, plain sections: 40mm (best economy)
  • Mass concrete, retaining walls: 40–63–80mm
  • Pumped concrete: MSA ≤ 1/3 of pump pipe diameter (100mm pipe → 32mm max → use 25–31.5mm)
  • Pavement concrete (IRC:58): 31.5mm specified

Economy Impact of MSA Selection

The cement saving from increasing MSA is significant:

At M30, 100mm slump, w/c 0.45:
10mm MSA: W = 222 L/m³ → C = 222/0.45 = 493 kg/m³
20mm MSA: W = 202 L/m³ → C = 202/0.45 = 449 kg/m³
40mm MSA: W = 176 L/m³ → C = 176/0.45 = 391 kg/m³

10mm → 40mm: saves 102 kg/m³ cement = ₹612/m³ at ₹6/kg
Select the largest MSA permitted by IS 456 Cl.5.3.1 for your section.

6.2 Aggregate Grading — Why It Matters

Aggregate grading (particle size distribution) affects the workability and paste requirement of concrete. Well-graded aggregate with a range of particle sizes packs more efficiently — smaller particles fill voids between larger ones, reducing the void space that paste must fill. Poorly graded aggregate (gap-graded or single-sized) has higher void content and needs more paste to achieve the same workability.

IS 383:2016 Fine Aggregate Zones — Practical Significance

IS 383:2016 classifies fine aggregate into four grading zones based on the percentage passing 600µm sieve:

Zone I (Coarse sand): 60–79% passing 600µm. Lower water demand. Needs lower FA% in mix. Good for concrete but may need more paste for cohesion. FM ≈ 3.0–3.5.
Zone II (Standard): 75–100% passing 600µm. IS 10262 Table 3 reference. Most common M-Sand specification. FM ≈ 2.6–2.9.
Zone III (Medium-fine): 85–100% passing 600µm. Higher water demand. Increase FA% slightly. FM ≈ 2.2–2.6.
Zone IV (Fine): 95–100% passing 600µm. Highest water demand. Not recommended for M30+ designed mix. FM ≈ 1.6–2.2. Avoid for structural concrete where possible.

River sand in India is commonly Zone II–III. M-Sand (crushed aggregate fines) is often Zone I–II. Zone IV (very fine) river sand from certain rivers increases water demand by 15–20 L/m³ compared to Zone II.

7. FA/CA Proportion Split — IS 10262:2019 Table 3

After the total aggregate volume (V_agg) is determined by the absolute volume method, it must be split between fine aggregate (FA) and coarse aggregate (CA). IS 10262:2019 Table 3 provides the percentage of FA by volume of total aggregate, as a function of MSA and FA zone.

← Scroll

MSA (mm) Zone I FA% Zone II FA% Zone III FA% Zone IV FA%
10mm 40 44 48 52
12.5mm 36 40 44 48
16mm 34 38 42 46
20mm 32 36 40 44
25mm 30 34 38 42
40mm 28 32 36 40

Highlighted cell: 20mm MSA, Zone II — 36% FA. Most common starting point for M25–M40 structural concrete.

Adjusting the FA/CA Split in Practice

The IS 10262 Table 3 value is a starting point for trial mixes. It assumes Zone II sand and standard crushed granite. Adjustments are made based on:

Workability Too Low

If the mix is harsh or has poor workability despite correct slump, increase FA% by 2–4% (more fine particles improve cohesion and flowability). Re-check: increasing FA reduces CA proportionally, so recalculate masses. More FA also means slightly higher water demand — check slump.

Segregation or Bleed

If concrete shows bleeding (water rising to surface) or segregation (coarse aggregate separating), reduce FA%. More CA and less FA typically reduces bleed. Also check that water content isn’t excessive — bleeding is primarily a symptom of excess water, not an FA/CA imbalance.

Pump Mixes

Pumpable concrete needs more paste and more fine material to lubricate the pipe walls. Increase FA% by 3–5% above Table 3 value. Also ensure paste volume is sufficient — lean pumped mixes (low cement) frequently block. Minimum paste volume ~30% for reliable pumping.

8. Durability-Governed Proportioning

For grades M25 and above in most exposure conditions, IS 456 Table 5 exposure class requirements impose tighter constraints on mix proportions than strength requirements alone. Understanding when durability governs — rather than strength — is essential to correct proportioning.

When Durability Governs

Durability governs the proportioning when the IS 456 Table 5 maximum w/c is lower than the w/c required for the target mean strength. For example:

  • M30 in Moderate exposure (max w/c 0.50): strength needs w/c ≈ 0.48; IS 456 allows 0.50. Strength governs slightly.
  • M30 in Severe exposure (max w/c 0.45): strength needs w/c ≈ 0.48; IS 456 limits to 0.45. Durability governs — must use lower w/c.
  • M30 in Very Severe exposure (max w/c 0.40): IS 456 limits w/c to 0.40 — 25 MPa stronger than strength requires. Durability overwhelmingly governs.

When durability governs, the resulting concrete will be stronger than specified (because using a lower w/c than strength needs produces higher strength). This strength reserve is not a problem — it is simply a consequence of the durability-first design approach mandated by IS 456.

The Two-Limit Framework — Always Take the Lower w/c

IS 10262:2019 Cl.5.3 is explicit: design w/c is the lower of the w/c from the strength-w/c relationship AND the IS 456 Table 5 maximum for the exposure class. Never use a w/c higher than both limits, even if the client objects to higher cement costs — the code mandates it for legally compliant structural concrete.

The minimum cement content (IS 456 Table 5) is a separate additional constraint — the design cement = max(C_calc, C_min). Both the maximum w/c and minimum cement must be satisfied simultaneously.

9. How Admixtures Change the Proportions

Chemical admixtures modify concrete properties by chemical or physical action at low dose rates. They do not change the fundamental proportioning approach — but they change the numbers significantly. IS 9103:1999 governs admixtures in India.

PCE Superplasticizer (Type F/G) — The Most Important

Polycarboxylate Ether (PCE) superplasticizers disperse cement particles through steric repulsion, allowing the same workability to be achieved at 20–35% less water. This water reduction allows proportional cement reduction (same w/c, less C = less W). The proportioning adjustment for PCE SP:

W_design = W_table × (1 − WR_fraction)
C_design = W_design / w/c

Example: M30, 20mm, 100mm slump, PCE 25% WR:
W_table = 202 L/m³
W_design = 202 × 0.75 = 151.5 → say 152 L/m³
C_design = 152 / 0.45 = 338 kg/m³
vs without PCE: C = 202/0.45 = 449 kg/m³
Saving: 111 kg/m³ cement = ~₹666/m³

Additionally, the SP liquid volume (typically 3–5 L/m³) must be included in the absolute volume calculation: V_SP = SP_mass / (Sg_SP × 1000).

Other Admixtures — Proportioning Adjustments

Retarder

Does not change proportions. Extends setting time without affecting water demand. No adjustment to water or cement content needed. Include volume in absolute volume check (typically 0.5–1.0 L/m³).

Air-Entraining Admixture (AEA)

Introduces 4–6% air by volume — significant volume that displaces both paste and aggregate. Two adjustments: (1) Reduce water by 5–8 L/m³ (air bubbles improve workability slightly); (2) V_agg is reduced by the air fraction, so FA and CA masses are lower. Check that target strength is still met — each 1% air reduces strength by approximately 4–5%.

SCM Additions (Fly Ash, GGBS, SF)

Each SCM has a different specific gravity from OPC — their volume must be calculated separately. GGBS (Sg 2.90) and Fly Ash (Sg 2.20) have lower Sg than OPC (Sg 3.15), so the same mass occupies more volume. Silica Fume (Sg 2.20) is additive to OPC rather than replacing it by volume — it occupies additional volume, reducing aggregate content.

10. Full Worked Example — M30, 100mm Slump, 20mm MSA

A complete IS 10262:2019 absolute volume mix design for the most common structural concrete specification: M30, Severe exposure, 100mm target slump, 20mm crushed granite, OPC 53, PCE SP at 1.0% bwoc with 22% water reduction, Zone II M-Sand.

Given Data

fck = 30 MPa | Exposure = Severe | Target slump = 100mm | MSA = 20mm
Cement: OPC 53, Sg = 3.15 | FA (M-Sand Zone II): Sg = 2.65
CA (Crushed Granite): Sg = 2.68 | PCE SP: Dose = 1.0% bwoc, Sg = 1.06, Solid = 40%
Entrapped air = 2.0%

1 Target Mean Strength

IS 10262 Table 1: for M30, S = 5.0 MPa

fcm = fck + 1.65 × S = 30 + 1.65 × 5.0 = 30 + 8.25 = 38.25 MPa

2 Design w/c Ratio

From strength-w/c relationship for OPC 53: w/c for fcm 38.25 MPa ≈ 0.47. IS 456 Table 5 maximum for Severe exposure: w/c ≤ 0.45. Use the lower value.

Strength-based: w/c ≈ 0.47
IS 456 Severe: w/c ≤ 0.45
Design w/c = min(0.47, 0.45) = 0.45

3 Design Free Water Content

IS 10262 Table 2: 20mm MSA, 76–100mm slump → 202 L/m³. PCE SP at 22% WR:

W_table = 202 L/m³ (crushed aggregate, 100mm slump, 20mm MSA)
PCE water reduction = 22%
W_design = 202 × (1 − 0.22) = 202 × 0.78 = 157.6 → say 158 L/m³

4 Cement Content

IS 456 Table 5 minimum for Severe exposure: 320 kg/m³.

C_calc = W / w/c = 158 / 0.45 = 351.1 kg/m³
IS 456 minimum (Severe) = 320 kg/m³
C_design = max(351.1, 320) = 351 kg/m³ [Strength governs]
Check max: 351 ≤ 550 kg/m³ ✅

5 Superplasticizer Volume & Water Correction

SP mass = C × dose = 351 × 0.010 = 3.51 kg/m³
SP volume = 3.51 / 1.06 = 3.31 L/m³ = 0.00331 m³/m³
SP free water = 3.31 × (1 − 0.40) = 1.99 L/m³
Batch water = 158.0 − 1.99 = 156.0 L/m³

6 Absolute Volumes

V_cement = 351 / (3.15 × 1000) = 0.1114 m³
V_water = 158 / 1000 = 0.1580 m³
V_air = 2.0% = 0.0200 m³
V_SP = 3.31 / 1000 = 0.0033 m³
────────────────────────────────────────────
Sum (paste) = 0.2927 m³ → Paste volume = 29.3% ✅
V_aggregate = 1.0000 − 0.2927 = 0.7073 m³

7 FA/CA Split (IS 10262 Table 3)

20mm MSA, Zone II FA → FA% = 36% of total aggregate volume

V_FA = 0.7073 × 0.36 = 0.2546 m³ → FA = 0.2546 × 2.65 × 1000 = 675 kg/m³
V_CA = 0.7073 × 0.64 = 0.4527 m³ → CA = 0.4527 × 2.68 × 1000 = 1213 kg/m³

8 Final Mix Design — Summary & Verification

OPC 53 Cement: 351 kg/m³
Batch Water: 156 L/m³
Fine Aggregate (SSD): 675 kg/m³
Coarse Aggregate(SSD):1213 kg/m³
PCE SP (liquid): 3.31 L/m³
─────────────────────────────────
Fresh density = 351 + 156 + 675 + 1213 + 3.51 = 2398.5 kg/m³

Verification (volume sum):
0.1114 + 0.1580 + 0.0200 + 0.0033 + 0.2546 + 0.4527 = 1.0000 m³ ✅

Mix ratio (1:FA:CA) = 1 : 1.92 : 3.46
Effective w/c = 156/351 = 0.444 (≤ 0.45 IS 456 ✅)
IS 456 min cement = 320 kg/m³; design = 351 ✅

✅ This Mix Design Is Now Ready for Trial Mix Verification

The calculated proportions above are the starting point for IS 10262:2019 Clause 7 trial mixes. Prepare at least three batches using the above proportions with your actual site materials, measure fresh slump and density, cast 6 cubes (150mm) per batch, cure at 27±2°C in water, and test at 7 days (expect ~28 MPa) and 28 days (expect ~38–40 MPa). If results are within acceptable range, this mix design is confirmed for production. If not, adjust w/c or water as described in the trial mix procedure section.